Mahshahr Fajr 2 gas & Steam Power Plant (4 X 164 MW )
 
by: SPEEDES Group

  Mahshahr Fajr 2 Steam and Power Plant Generation is located at Mahshahr petrochemical zone . This project consist of 4 gas turbine generator with the capacity of 156 MW each designed to generate about 630 MW of electrical power and 740 ton steam for transmissioning to Fajr 2 petrochemical Power plant. Work Scope of contract is divided into technical and non-technical parts as follows:

Owner:

Iran Petrochemical Company

Duration:

36 Months From 9th October 2007

Employer:

Management of Iran Power Plant Co.. (MAPNA3)

The power plant is located in Fajr 2 petrochemical free zone in Mahshahr. Scope of work of contract consists of following structures:

-          Turbine Hall including TG foundations, steel structure, slab, Equipment foundation, wall and roof cladding.

-          2 units HRSG foundations related to steam part

-          Stack foundations

-          Fin fan coolers structures

-          Central control building & CUS building with concrete structure

-          Main and Auxiliary transformer foundation with fire wall

-          Fuel tanks, Unloading Station, Unloading Pump house ¡Forwarding Pump house  

-          Pipe and cable racks

    View Projects Images