Montazer Ghaem Power Plant
by: SPEEDES Group
Despite the fact that Constructive process of enlarging 230 KV post of Manzar Ghaem synthetic cycle power plant |
|
|
Owner:
|
Iran Power Development Company (IPDC) |
Duration:
|
4 Months From1988 |
Employer:
|
Iran Power Development Company (IPDC) |
Consultant:
|
Moshanir Power Engineering Consultant |
|
Despite the fact that Constructive process of enlarging 230 KV post of Manzar Ghaem synthetic cycle power plant , in one hand accomplished in impossible way of Cutting off the electricity because of high consuming and in the other hand because of electrical loading of the next posts needs some especial surveillance , in this project all process such as :temporary and continual earth net ,delving , foundational fabrication and execution of network canal was completely done attentively and delicacy with ideal rate in the best way .
|
View Projects Images |
Back |
|
|
|
|