Rudeshur Power Plant (3 X 250 MW )
 
by: SPEEDES Group

  Rudeshur 2000MW Power plant is located at km 40 of Tehran-Saveh highway. The 1st phase of this project consists of 3 gas turbine generator with the capacity of 250 MW each designed to generate about 750 MW of electrical power for the export to national grid via a 400kv outdoor substation. Scope of work of contract is divided into two technical and non technical parts as follows:

Owner:

Mahtab Gostar Company

Duration:

15 Months from March 2005

Employer:

European Energy System ( EES )
Consultant: Fichtner Co. & Daryapala

Rudeshur 2000MW Power Plant is located at km 40 south of Tehran. The 1st phase of this project consist of 3 gas turbine generator with the capacity of 250 MW each designed to generate about 750 MW of electrical power for the export to national grid via a 400kv outdoor substation. Scope of work of contract is divided into two technical and non technical buildings as follows:

Technical Buildings:

Turbine hall: with steel structure in three units. GTG foundation and other equipment foundation

CCB: with concrete structures & Emergency diesel generator

3 bays 400 KV substation

Fuel oil system includes: tanks, fuel forwarding, pump house, unloading pump house, unloading station, fuel oil tank and heating building.

Water & waste water systems.

Fire fighting system.

Non Technical Buildings:

Workshop, store, administration building, canteen, access & patrol roads, parking, flood channel and fences around the power plant.